    Default AFG Extension Request

    Any of the grant gurus have experience with this? The online tutorial says:

    Amendment Requests
    Request to Extend the Period of Performance

    The amendment request must include the following information:

    * Reason for the extension request

    * Current status of your project

    * Specific timeframe when the project will be completed

    * Explanation of how the remaining funds will be expended
    -----------------------------
    Here's the deal. We are worried Draeger is not going to deliver by their July 17 deadline. We have lots of written promises going back several months, but now we are starting to think they may not be able to deliver. We need to either cut them loose and go with another manufacturer, or somehow hold their feet to the fire. In either case, we are almost 1 month away from the deadline. We need at least a couple of weeks (or at least one working week) to request money, cut the check and work through the borough to get everything done. Thus, accepting delivery on July 17 doesn't cut it.

    Any suggestions on how to proceed are appreciated.

    I feel like this:


  2. #2
    MembersZone Subscriber ktb9780's Avatar
    Join Date
    Dec 2004
    Location
    Auburndale, FL
    Posts
    6,041

    Default

    Quote Originally Posted by JD1234 View Post
    Any of the grant gurus have experience with this? The online tutorial says:

    Amendment Requests
    Request to Extend the Period of Performance

    The amendment request must include the following information:

    * Reason for the extension request

    * Current status of your project

    * Specific timeframe when the project will be completed

    * Explanation of how the remaining funds will be expended
    -----------------------------
    Here's the deal. We are worried Draeger is not going to deliver by their July 17 deadline. We have lots of written promises going back several months, but now we are starting to think they may not be able to deliver. We need to either cut them loose and go with another manufacturer, or somehow hold their feet to the fire. In either case, we are almost 1 month away from the deadline. We need at least a couple of weeks (or at least one working week) to request money, cut the check and work through the borough to get everything done. Thus, accepting delivery on July 17 doesn't cut it.

    Any suggestions on how to proceed are appreciated.

    I feel like this:
    Pick up the phone and call your Fire Program Specialist assigned to your grant or send them an email and explain same to them and ask them what they would prefer that you do.
    Kurt Bradley
    Public Safety Grants Consultant

    "Never Trade Skill for Luck"

  3. #3
    Forum Member
    Join Date
    Feb 2007
    Location
    NJ
    Posts
    224

    Default

    Thanks, Kurt. Done.

    Perhaps I should have asked if anyone has had success in getting an extension in the past.

  4. #4
    MembersZone Subscriber ktb9780's Avatar
    Join Date
    Dec 2004
    Location
    Auburndale, FL
    Posts
    6,041

    Default

    Quote Originally Posted by JD1234 View Post
    Thanks, Kurt. Done.

    Perhaps I should have asked if anyone has had success in getting an extension in the past.
    Usually not a problem if it is not your fault but have to show you are proactive at resolving issue and have a plan "b" in mind.
    Kurt Bradley
    Public Safety Grants Consultant

    "Never Trade Skill for Luck"

  5. #5
    MembersZone Subscriber
    Join Date
    Jan 2005
    Posts
    3,733

    Default

    Quote Originally Posted by JD1234 View Post
    Thanks, Kurt. Done.

    Perhaps I should have asked if anyone has had success in getting an extension in the past.
    In 2005 we recieved a 2 month extension for our brush truck. As Kurt pointed out get in touch with your FPS for help. I explained on the phone the issue for the delay and he had no problem with us submitting an extension for the POP. His only requirement was to do this one time.

  6. #6
    FH Mag/.com Contributor
    Join Date
    Feb 2002
    Location
    Cypress, TX
    Posts
    7,288

    Default

    Actually if you go back far enough they've basically said that there will be no extensions on SCBA if there are other 2007 compliant packs on the market. Doesn't mean they're going to hold to it, but be prepared to defend your position that those are the only packs that will work for you.

    I'm surprised you're having issues with them, thought most everyone was on track by now.

  7. #7
    Forum Member
    Join Date
    Feb 2007
    Location
    NJ
    Posts
    224

    Default

    Brian, do you have any specifics on early delivery dates from Draeger?

    We have a promised delivery date of June 30, but we have reason to be concerned that if June 30 passes without delivery, we will not be in a position to request an extension.

    What is considered "complete" by AFG standards? Like I said above, it will take about 1 week to do the funds transfer through our borough, so accepting the packs on July 17 does not cut it. I understand we have a period of time to complete our report after the project is complete.

    These are the only packs that work for us because all the other manufacturers were well over the $5,000 limit when we quoted them.

    I have a note into our program representative detailing our situation, and hopefully we will get the extension as an insurance policy.

  8. #8
    Forum Member
    Join Date
    Dec 2006
    Location
    Springfield, NJ
    Posts
    82

    Default

    Quote Originally Posted by JD1234 View Post
    considered "complete" by AFG standards? Like I said above, it will take about 1 week to do the funds transfer through our borough, so accepting the packs on July 17 does not cut it. I understand we have a period of time to complete our report after the project is complete.
    Not that I would want to cut it that close either but you can pay bills incurred during your period-of-performance after that time, not just do the closeout reports then. So, if they deliver during your grant period, you can still pay them a week or two after the grant period is over.

    That said, have you told Drager "hey, its federal money we have to send by July 1st or we loose the money and you loose our order?"
    Apu
    http://www.SpringfieldFAS.org/
    http://www.VolunteerEMS.org/
    "The views expressed are my own."

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Wooden extension ladder v. aluminum extension
    By banksvfd201 in forum Firefighters Forum
    Replies: 2
    Last Post: 01-09-2008, 06:55 AM
  2. AFG Extension
    By FF4020 in forum Federal FIRE ACT Grants & Funding
    Replies: 1
    Last Post: 11-02-2006, 05:51 PM
  3. Request for Firefighters for Fire Suppression (NOT THE FEMA REQUEST!)
    By rjtoc2 in forum Hurricane Katrina & Rita Forums
    Replies: 6
    Last Post: 09-06-2005, 09:21 AM
  4. Rescue Pumper request...what if any equipment can be part of our grant request?
    By FyredUp in forum Federal FIRE ACT Grants & Funding
    Replies: 8
    Last Post: 03-30-2004, 08:05 AM
  5. Parts of an extension ladder
    By Lt Fenstermaker in forum Emergency Services Training
    Replies: 3
    Last Post: 11-26-2000, 10:25 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts