What justifies a need to request a revision.
Here's the situation:
Our grant was for 14 portable radios with vehicle chargers and included installation charges for the chargers. We are looking at the following changes: half hardwire chargers and half cigarette lighter chargers (half of the radios are for officers to have in their POV) 8 spare batteries and extended warranties for the radios. The money is almost identical so my question is do I need to get approval before making these changes?
+ Reply to Thread
Results 1 to 2 of 2
Thread: Revision Requests
-
03-09-2003, 10:28 PM #1MembersZone Subscriber
- Join Date
- Mar 2001
- Location
- WHITE STONE, VA. USA
- Posts
- 9
Revision Requests
-
03-09-2003, 10:53 PM #2Administrator
- Join Date
- Jun 2006
- Posts
- 2,480
You just need to call your FEMA grant representative to get this approval.